Published on Tuesday, 14 October 2025 at 11:25:00 AM
Works are about to commence on the Ranford Shared Path - an upgrade to the existing path that will enhance the connection between Ranford Pool and Hotham Park, and establish a continuous route for cyclists, pedestrians, and users with accessibility needs.
Project Timeline:
| 15 October 2025 |
Demolition of existing path, with temporary path in place. |
| 04 December 2025 |
Drainage and earthworks |
| 02 March 2026 |
Asphalt works |
| 23 March 2026 |
Kerbing |
| 03 April 2026 |
Line marking and signage |
| 24 April 2026 |
Project completion |
The upgraded Shared Path will be available for use in early May 2026 and will be celebrated with an Opening Ceremony.